Module 2 · Risk Management · Lesson 13 of 42

Qualitative risk assessments, risk registers and heat maps

Rate risks by likelihood and impact, record them in a risk register, and visualize them with a heat map or risk matrix.

In this lesson · about 16 minutes

  • Tell qualitative from quantitative risk assessment
  • Rate a risk's severity from its likelihood and impact
  • List what goes into a risk register
  • Read a risk heat map and a risk matrix

Qualitative vs quantitative

A quantitative assessment uses hard numbers, usually money (SLE, ARO, ALE). A qualitative assessment uses judgment: people rate each threat's likelihood and impact as Low, Medium or High (or on a 1–5 scale) and combine them into a severity rating. Because it's subjective, two assessors may rate the same risk differently. That doesn't make it less useful: it's faster, needs no dollar figures, and is the most common approach in practice.

The risk register

A risk register is the central list of an organization's risks. You might keep one for the whole organization and others for a department or a project, but each contains the same kind of information:

#Date addedRiskLikelihoodImpactOwnerMitigation
12026-03-02Ransomware on file serversMediumHighIT managerOffline backups; incident response plan IRP-04
22026-03-02Laptop theftHighLowFacilities leadFull disk encryption
32026-04-15Data center floodLowHighOperations directorRaised floor; off-site replica
42026-05-20Phishing steals staff credentialsHighMediumSecurity leadAwareness training; MFA

Registers are usually qualitative (ratings), though some also record dollar values. The owner is the person accountable for the risk, and the mitigation can point to a control or to an incident response plan (IRP).

Heat maps and risk matrices

A risk heat map plots each risk from the register on a grid of likelihood against impact. Colors show severity: green is low, amber is medium, red is high. The number in each cell refers back to the risk's number in the register.

Likelihood ↓ / Impact →LowMediumHigh
High24
Medium1
Low3

Risks toward the top right (likely and damaging) get attention first. Here, risk 4 (phishing) and risk 1 (ransomware) are the priorities.

A risk matrix is the same grid without the colors: it plots severity levels and can hold the risk details in one place. Think of it as a heat map minus the colors.

Performance-based question (PBQ)

Rate the risks

You're adding new entries to the risk register. Use this rule: High likelihood + High impact = Critical; one High and one Medium = High; both Medium, or one High and one Low = Medium; anything lower = Low.

Choose the severity for each risk.

  • Unpatched public web server (likelihood High, impact High)
  • Office printer jams (likelihood High, impact Low)
  • Insider copies the customer list (likelihood Medium, impact High)
  • Meteor strikes the head office (likelihood Low, impact High)
  • Staff visit a blocked gaming site (likelihood Low, impact Low)
  • Power outage in a storm-prone area (likelihood Medium, impact Medium)
0 of 6 answered

Sorting drill

Qualitative or quantitative?

Sort each statement by the kind of assessment it describes.

  • Likelihood: High, Impact: Medium
  • ALE = $6,000 per year
  • A color-coded heat map
  • SLE = AV × EF
  • The team agrees the risk 'feels' severe
  • Exposure factor of 25%

0 of 6 sorted

Check your understanding0 of 6 correct

Question 1

1.What is a qualitative risk assessment mainly based on?

Question 2

2.Which of these is LEAST likely to be a field in a risk register?

Question 3

3.On a risk heat map, what do the red cells usually mean?

Question 4

4.What is the main difference between a risk heat map and a risk matrix?

Question 5

5.Two analysts rate the same risk differently. Which type of assessment does this show?

Question 6

6.Which risk should be addressed first?

Quiz score: 0 of 6

Tip: answer every quiz question correctly first.