Module 2 · Risk Management · Lesson 12 of 42

Risk assessments and risk treatments

Scope and run a risk assessment, recognise environmental, person-made, internal and external risks, and choose between mitigate, transfer, avoid and accept.

In this lesson · about 18 minutes

  • Scope a risk assessment to the whole organization or to a project, department, system or merger
  • Describe the risk assessment process, residual risk and continuous monitoring
  • Classify risks as environmental, person-made, internal or external
  • Choose the right risk treatment: mitigate, transfer, avoid or accept

You can't manage risk you don't know about. A risk assessment finds and prioritizes the threats to your assets, so you can decide what to do about each one.

Scope: what are you assessing?

An assessment doesn't have to cover the whole enterprise. Large organizations often assess a smaller piece:

  • A project: is it worth starting at all?
  • A single department.
  • A specific system that's about to go live.
  • A merger or acquisition: what risks come with the company you're buying?

Typical things to assess include individual servers, legacy systems (older systems with known vulnerabilities that you still need for some software), the theft of intellectual property (IP), and software licensing compliance: using software outside its license terms can lead to fines.

The process

  1. Know the threats. Assessors need current awareness of threats, drawn from the threat intelligence sources covered earlier.
  2. Identify and prioritize the risks to each asset.
  3. Evaluate the existing security controls and decide on a treatment for each risk.
  4. Accept the residual risk. Some risk always remains, just as there's a small risk every time you leave home. You don't stay in; you reduce the risk and carry on.
  5. Monitor continuously. A control that works today may not work in six months as attackers change tactics, so review controls periodically.

Types of risk

TypeExamples
EnvironmentalHurricanes, floods, wildfires and the power outages they cause
Person-madeRiots, terrorism, intentional sabotage
InternalA malicious insider, or an innocent employee who opens an infected file and releases malware
ExternalNation-states or competitors launching a distributed denial-of-service (DDoS) attack that floods your servers so legitimate users can't reach them

Risk treatments: what do you do about it?

TreatmentMeaningExample
Mitigate (reduce)Put controls in place before the risky activity to lower its likelihood or impactAdd MFA, patch, install a firewall
Transfer (share)Move some of the financial impact to another partyFire insurance, cybersecurity insurance
AvoidDon't do the activity at all, because the benefit isn't worth the riskCancel a project or retire an insecure system
AcceptTake the risk as it is, with no new control, because it falls within the organization's risk appetiteAccept the small risk of a low-value kiosk failing

Mitigating and accepting are not the same. Mitigation adds a control; acceptance knowingly adds none.

Decision scenario

The aging payroll server

You are the risk analyst presenting to the IT steering committee.

The payroll system runs on a legacy server with known vulnerabilities. A replacement is budgeted for next year. Until then, the committee wants your recommendation.

What do you recommend?

0 of 4 options explored. Try the others to see how each would play out.

Performance-based question (PBQ)

Name the risk treatment

The risk committee has made decisions on six entries in the risk register. Record the treatment for each one.

Choose the risk treatment for each decision.

  • Buy a cybersecurity insurance policy to cover ransomware losses
  • Cancel plans to store customer card numbers; use the payment provider's tokens instead
  • Deploy endpoint protection and email filtering against malware
  • Leave the lobby's digital sign unpatched; the risk is within appetite
  • Add a backup generator for the server room in a hurricane zone
  • Outsource card processing to a provider that contractually takes on breach liability
0 of 6 answered

Sorting drill

Which type of risk?

Sort each risk into its type.

  • A flood knocks out power to the data center
  • Rioters damage the branch office
  • An employee opens an infected attachment by mistake
  • A competitor launches a DDoS attack on the online store
  • A hurricane damages the warehouse roof
  • A disgruntled administrator deletes backups

0 of 6 sorted

Check your understanding0 of 7 correct

Question 1

1.A company is about to acquire a smaller firm and wants to know what security problems come with it. What should it do?

Question 2

2.Why must security controls be reviewed periodically?

Question 3

3.Which risk treatment is cyber insurance?

Question 4

4.A company decides not to launch a product because the security risk outweighs the expected profit. Which treatment is this?

Question 5

5.What is the difference between risk acceptance and risk mitigation?

Question 6

6.Using software beyond the terms of its license is mainly which kind of risk?

Question 7

7.A hurricane causes a two-day power outage at the head office. What type of risk is this?

Quiz score: 0 of 7

Tip: answer every quiz question correctly first.

Noviq Academy is free and for learning. This course is independent and is not affiliated with or endorsed by CompTIA. CompTIA and Security+ are trademarks of CompTIA, Inc. Exam details such as price and policies change; confirm them on CompTIA's website before you book.